NJ · HighNew Jersey regulators seek input on data center power rules; responses due No…PA · MediumPennsylvania court holds a driveway linking an existing school to a road is n…NJ · LowNew Jersey spells out sampling and data needed for site-specific soil cleanup…NY · MediumNew York City bulletins cap lifetime yard and height additions to existing bu…PA · MediumFederal court upholds Pennsylvania permits for Transco pipeline, ties environ…NY · MediumNew York offers counties up to $1.5 million for infrastructure that supports…NY · LowNew York approves two utility heating and cooling networks in Buffalo and Hav…NY · MediumNew York lays out $200 million solar incentive plan favoring brownfields, lan…PA · MediumPennsylvania governor seeks role in case to make PPL data centers pay grid up…NY · HighNew York denies a Columbia County solar permit over flood and wetland gaps
HighNew Jersey

New Jersey regulators seek input on data center power rules; responses due November 13

Utility regulators asked how to set the size threshold, grid connection priority, emergency curtailment and 10-year payment guarantees that will govern electric service to large data centers under a July law.

New Jersey has begun deciding which data centers fall under new electric service rules and on what terms utilities will serve them. On October 19, 2026, staff of the New Jersey Board of Public Utilities (the “Board”) issued a Request for Information (“RFI”), In re Implementation of the Data Center Fair Share Act, Docket No. EO26080463, to implement P.L. 2026, c. 32 (the “Act”), N.J.S.A. 48:7-6.2. Responses are due by 5:00 p.m. on November 13, 2026, and a virtual stakeholder meeting is set for November 4, 2026.

P.L. 2026, c. 32, § 1 (N.J.S.A. 48:7-6.2); In re Implementation of the Data Center Fair Share Act, Docket No. EO26080463 (N.J. Bd. of Pub. Utils. Staff Oct. 19, 2026) (request for information)

More on New Jersey: rulebook · compliance calendar · funding and incentives · open comment periods