NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…

Briefings

What changed in environmental, land-use and permitting rules for development in New Jersey, New York, Connecticut and Pennsylvania: what happened, who is affected and the next date that matters.

  1. HighNew Jersey

    Federal: New Jersey and Pennsylvania data centers seeking more power would face one-year grid study

    PJM asked federal regulators on November 16, 2026, to study large loads and new power plants together in a 12-month process and to add three transmission services for large loads.

  2. MediumNew Jersey

    Federal: Grid operator seeks rule keeping New Jersey and Pennsylvania data centers online during grid disturbances

    PJM asked federal regulators on November 16, 2026 to require data centers of 50 megawatts or more to ride through grid disturbances, with a requested January 16, 2027 start.

  3. HighNew Jersey

    New Jersey regulators seek input on data center power rules; responses due November 13

    Utility regulators asked how to set the size threshold, grid connection priority, emergency curtailment and 10-year payment guarantees that will govern electric service to large data centers under a July law.

  4. MediumNew Jersey

    New Jersey tells towns how to negotiate data center benefit deals and property tax breaks

    State guidance lists what towns should cover in community benefits agreements with data center developers, restates labor rules for data center construction, and urges caution on long-term tax exemptions.

  5. MediumMiddlesex County, NJ

    New Jersey weighs diesel generator permit for South Brunswick data center; comments now due November 9

    A draft state air permit for twelve emergency diesel generators at a data center under construction on Route 1 drew a crowded hearing, a neighboring town's objection and a longer comment period.

  6. MediumNew Jersey

    New Jersey halves AI data center tax credits and closes the program to new applicants

    A new law cuts the state's artificial intelligence and data center credit pool from $500 million to $250 million; the state says the remaining credits are fully allocated.

  7. MediumNew Jersey

    New Jersey Pinelands towns ban data centers as state commission lets eleven local bans take effect

    By the end of September 2026, the Pinelands Commission had cleared data center bans in eleven towns and a moratorium in a twelfth, with more ordinances awaiting review.

  8. HighCumberland County, NJ

    New Jersey fines Vineland data center $1.07 million for running 62 unpermitted gas generators

    The state's largest penalty against a data center gives the developer 45 days to obtain air permits or stop running the generators, a warning for projects using on-site bridge power.

  9. HighNew Jersey

    Federal regulators reject plan to curtail New Jersey's new large loads first in grid emergencies

    On September 29, 2026 FERC accepted the regional grid operator's one-time capacity backstop but suspended it to February 28, 2027 for a paper hearing. On October 9 FERC rejected a separate PJM service that would have curtailed new large loads first, accepting only a 50-megawatt large-load definition and a registry.

  10. HighNew Jersey

    New Jersey sets path for data center electric tariffs requiring 10-year payment guarantees and twice-yearly reporting

    Two 2026 laws reach New Jersey data centers: a July 7 tariff law with an 85 percent, 10-year payment guarantee and priority curtailment, and an August 27 law requiring semiannual energy and water reports to the BPU. Board standards are due within 12 months of July 7.