NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…NY · HighNew York regulators weigh two more years of shared grid upgrade costs for sol…NY · HighNew York ends free gas line allowance for new homes December 19 and proposes…NJ · HighNew Jersey utility board will hear solar developer's bid to override a town's…PA · MediumPennsylvania high court bars 'minor' use variances, closing a route around zo…NY · LowBronx Kingsbridge Armory developer applies for New York brownfield program; c…NY · HighNew York proposes PFAS soil cleanup objectives and history-based PFAS testing…PA · MediumPennsylvania court lets Philadelphia City Council appeal zoning approvals thr…
HighNew Jersey

Federal: New Jersey and Pennsylvania data centers seeking more power would face one-year grid study

PJM asked federal regulators on November 16, 2026, to study large loads and new power plants together in a 12-month process and to add three transmission services for large loads.

Data centers and other large sites in New Jersey and Pennsylvania would need a grid study, run in a one-year cycle alongside new power plants, before their transmission service could rise above a registered baseline. PJM Interconnection, L.L.C. ("PJM"), the federally regulated grid operator whose territory includes both states, asked the Federal Energy Regulatory Commission ("FERC") on November 16, 2026, to approve tariff changes creating a "Fast Energization Process" that would study transmission service for large loads and new generator connections together in a single 12-month process. PJM Interconnection, L.L.C., Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period, FERC Docket No. ER27-531-000 (filed Nov. 16, 2026). The filing is a proposal under section 205 of the Federal Power Act, 16 U.S.C. § 824d, and is not in force.

PJM Interconnection, L.L.C., Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period, FERC Docket No. ER27-531-000 (filed Nov. 16, 2026); 16 U.S.C. § 824d; PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026); PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026); PJM Interconnection, L.L.C., 197 FERC ¶ 61,019 (2026)