New York regulators weigh two more years of shared grid upgrade costs for solar and storage
A petition before the Public Service Commission would keep the cost-sharing rule for shared substation upgrades through April 30, 2029; comments are requested by January 19, 2027.
Developers of community solar, commercial rooftop solar and battery projects larger than 50 kilowatts and up to 5 megawatts in New York face the end of the rule that lets them share the cost of utility substation upgrades on April 14, 2027, unless regulators extend it. On November 18, 2026, the New York State Public Service Commission (the "Commission") published notice in the State Register that it is considering a petition to continue the "Cost Sharing 2.0 mechanism" for two years. N.Y. St. Reg., Nov. 18, 2026, at 18 (I.D. No. PSC-46-26-00007-P); Petition of NYSEIA, Industry Parties, and the Joint Utilities to Extend the Cost-Sharing 2.0 Mechanism, Case 20-E-0543 (N.Y. Pub. Serv. Comm'n filed Oct. 28, 2026).
N.Y. St. Reg., Nov. 18, 2026, at 18 (I.D. No. PSC-46-26-00007-P); Case 20-E-0543 (N.Y. Pub. Serv. Comm'n)