NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…
HighCumberland County, NJ

New Jersey fines Vineland data center $1.07 million for running 62 unpermitted gas generators

The state's largest penalty against a data center gives the developer 45 days to obtain air permits or stop running the generators, a warning for projects using on-site bridge power.

Data center developers that run on-site gas generators while waiting for grid power or permanent equipment now have a concrete measure of what operating them without a New Jersey air permit can cost. On September 22, 2026, the New Jersey Department of Environmental Protection (“DEP”) issued an Administrative Order and Notice of Civil Administrative Penalty Assessment assessing a $1.07 million civil administrative penalty against Data One (DataOne) for operating 62 large natural gas generators at its Vineland data center without the permits required under the Air Pollution Control Act, N.J. Stat. Ann. § 26:2C-1 et seq., according to a statement by Governor Mikie Sherrill that describes it as the largest enforcement action against a data center in the state's history.

N.J. Admin. Code §§ 7:27-8.2(c)(21), 7:27-8.3(a)-(b); N.J. Stat. Ann. §§ 26:2C-14.1, 26:2C-19(b)