Federal: Grid operator seeks rule keeping New Jersey and Pennsylvania data centers online during grid disturbances
PJM asked federal regulators on November 16, 2026 to require data centers of 50 megawatts or more to ride through grid disturbances, with a requested January 16, 2027 start.
Under a proposal now before federal regulators, data center developers in New Jersey and Pennsylvania would have to design new campuses, and bring operating ones into line, so that they stay connected to the grid through voltage and frequency disturbances instead of switching to onsite generators. In a filing on November 16, 2026, PJM Interconnection, L.L.C. ("PJM"), the regional grid operator whose territory includes New Jersey and Pennsylvania, asked the Federal Energy Regulatory Commission ("FERC") to amend its tariff to impose voltage and frequency "ride-through" requirements on a new class of customer, the "Large Computational Load," which PJM describes as facilities of 50 megawatts ("MW") or more.
PJM Interconnection, L.L.C., tariff filing on large computational load ride-through (filed with FERC Nov. 16, 2026); 16 U.S.C. § 824d; PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026); PJM Interconnection, L.L.C., 196 FERC ¶ 61,214 (2026)