Federal regulators reject plan to curtail New Jersey's new large loads first in grid emergencies
On September 29, 2026 FERC accepted the regional grid operator's one-time capacity backstop but suspended it to February 28, 2027 for a paper hearing. On October 9 FERC rejected a separate PJM service that would have curtailed new large loads first, accepting only a 50-megawatt large-load definition and a registry.
On September 29, 2026 the Federal Energy Regulatory Commission ("FERC") issued an order in Docket Nos. ER26-3380-000 and EL26-108-000 on the Reliability Backstop Procurement ("RBP") that PJM Interconnection, L.L.C. ("PJM"), the regional grid operator serving New Jersey, filed on July 31, 2026 and supplemented on August 14, 2026. FERC accepted the proposal for filing, suspended it for five months, effective February 28, 2027 and subject to refund, and set a paper hearing. A second PJM filing, Docket No. ER26-3515-000, would have created an Interim Resource Adequacy Service ("IRAS") for new large loads; on October 9, 2026 FERC rejected it, accepting only PJM's definition of a Large Load and its Large Load Registry, effective October 12, 2026.
FERC Docket Nos. ER26-3380-000 and EL26-108-000 (order of Sept. 29, 2026); FERC Docket No. ER26-3515-000; PJM Board decisional letter (July 27, 2026)