Briefings
What changed in environmental, land-use and permitting rules for development in New Jersey, New York, Connecticut and Pennsylvania: what happened, who is affected and the next date that matters.
- MediumNew Jersey
New Jersey's carbon cap hearings have passed; comments on the tighter limit close November 7
A pending state proposal would align New Jersey’s carbon allowance program with the regional model rule from January 2027; comments close November 7, and a separate October 15 hearing was set to address allowance prices and bills.
ProposedAir & climate - MediumMiddlesex County, NJ
New Jersey weighs diesel generator permit for South Brunswick data center; comments now due November 9
A draft state air permit for twelve emergency diesel generators at a data center under construction on Route 1 drew a crowded hearing, a neighboring town's objection and a longer comment period.
ProposedData centersAir & climate - HighCumberland County, NJ
New Jersey fines Vineland data center $1.07 million for running 62 unpermitted gas generators
The state's largest penalty against a data center gives the developer 45 days to obtain air permits or stop running the generators, a warning for projects using on-site bridge power.