New Jersey holds October 15 hearings on a tighter power plant carbon cap from 2027
A pending state proposal would align New Jersey’s carbon allowance program with the regional model rule from January 2027; comments close November 7, and a separate hearing addresses allowance prices and bills.
ProposedAir & climateEnergy & grid - MediumMiddlesex County, NJ
New Jersey weighs diesel generator permit for South Brunswick data center; comments now due November 9
A draft state air permit for twelve emergency diesel generators at a data center under construction on Route 1 drew a crowded hearing, a neighboring town's objection and a longer comment period.
ProposedData centersAir & climate - HighCumberland County, NJ
New Jersey fines Vineland data center $1.07 million for running 62 unpermitted gas generators
The state's largest penalty against a data center gives the developer 45 days to obtain air permits or stop running the generators, a warning for projects using on-site bridge power.