Federal: New England plan would make data centers line up new power or curb use
New England's grid operator asked federal regulators to approve three service types for loads of 50 megawatts or more and a study process starting June 1, 2027; Connecticut projects would be covered.
Data center developers looking at Connecticut sites would have to line up new power supply to get firm grid service, or accept service that is cut back when power prices run high, under a regional proposal now before federal regulators. ISO New England Inc. ("ISO-NE") announced on November 13, 2026, that it, the New England Power Pool and the Participating Transmission Owners Administrative Committee had jointly filed the proposal that week with the Federal Energy Regulatory Commission ("FERC"), in response to the show cause order FERC issued on June 18, 2026, in ISO New England Inc., 195 FERC ¶ 61,215 (2026) (Docket No. EL26-72-000).
ISO New England Inc., 195 FERC ¶ 61,215 (2026), Docket No. EL26-72-000; 16 U.S.C. §§ 824d, 824e