NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
HighNew Jersey

Federal: Appeals court voids New Jersey water certification for Raritan Bay gas pipeline expansion

The Third Circuit sent the Northeast Supply Enhancement certification back to New Jersey regulators, holding that monitoring plans needing only “review” and unexplained contaminant findings could not support it.

Pipeline and other energy developers whose projects need a New Jersey water quality certification now face a federal appeals court ruling that conditions deferring key plans to later agency “review” cannot carry an approval. In a federal decision, the U.S. Court of Appeals for the Third Circuit on September 8, 2026 vacated the New Jersey Department of Environmental Protection's (“NJDEP”) certification for Transcontinental Gas Pipe Line Company's Northeast Supply Enhancement (“NESE”) project and remanded it to the agency. Nat. Res. Def. Council, Inc. v. N.J. Dep't of Env't Prot., Nos. 26-1252 & 26-1253 (3d Cir. Sept. 8, 2026) (precedential).

Nat. Res. Def. Council, Inc. v. N.J. Dep't of Env't Prot., Nos. 26-1252 & 26-1253 (3d Cir. Sept. 8, 2026); 33 U.S.C. § 1341; 15 U.S.C. § 717r(d)(1); N.J. Admin. Code § 7:7-12.7

More on New Jersey: rulebook · compliance calendar · funding and incentives · open comment periods

Federal: Appeals court voids New Jersey water certification for Raritan Bay gas pipeline expansion — EnvironmentalShortcut