NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…
HighPennsylvania

Pennsylvania proposes cutting power to data centers first when the regional grid runs short

State utility regulators propose that utilities curtail large computing loads lacking their own new capacity before other customers in grid emergencies; comments are due 30 days after Bulletin publication.

Data center developers in Pennsylvania that have not brought new generating capacity for their full demand would be the first customers switched off when the regional grid runs short, under a proposal from state regulators. On October 1, 2026, the Pennsylvania Public Utility Commission (the “PUC”) entered a Tentative Order, Electric Distribution Company Interim Resource Adequacy Service, Pre-Emergency and Emergency Response Provisions, Docket No. M-2026-3064961 (Pa. P.U.C. Oct. 1, 2026), proposing that electric distribution companies (“EDCs”), the utilities that deliver power to customers, revise their emergency load control procedures under 52 Pa. Code § 57.52 so that large computing loads are curtailed before other customers. The order is a proposal and is not in force; comments are due 30 days after its publication in the Pennsylvania Bulletin.

Tentative Order, Electric Distribution Company Interim Resource Adequacy Service, Pre-Emergency and Emergency Response Provisions, Docket No. M-2026-3064961 (Pa. P.U.C. Oct. 1, 2026); 52 Pa. Code § 57.52; 66 Pa.C.S. § 1505(b)

More on Pennsylvania: rulebook · compliance calendar · funding and incentives · open comment periods