NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
HighPennsylvania

Pennsylvania regulators adopt model tariff guidance covering collateral and five-year terms for loads over 50 megawatts

The Public Utility Commission adopted a model tariff for large electric customers on April 30, 2026. It is guidance for each utility's own filing, not a rule, but it points to collateral, a five-year minimum term, 48 months' notice of exit and public interconnection queues.

On April 30, 2026, the Pennsylvania Public Utility Commission ("PUC") voted 5-0 to adopt a final order establishing a model tariff framework for large electric customers, at Docket No. M-2025-3054271. The Commission released the revised final order on May 13, 2026. It applies to customers with load over 50 megawatts ("MW") individually, or 100 MW in aggregate, and it addresses who pays for the grid upgrades such a customer causes, what security a utility may require, how long the customer commits to take service, and how the utility reports its queue of large-load requests.

Pa. PUC, Docket No. M-2025-3054271, Final Order (adopted April 30, 2026; released May 13, 2026)

More on Pennsylvania: rulebook · compliance calendar · funding and incentives · open comment periods

Pennsylvania regulators adopt model tariff guidance covering collateral and five-year terms for loads over 50 megawatts — EnvironmentalShortcut