NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
MediumNew York

New York regulator opens large-load grid connection review; technical conference due by December 31, 2026

A February 12, 2026 order opened a Public Service Commission proceeding on how to connect data centers and other large loads, including who pays for upgrades. Comments have closed; a staff technical conference is due before December 31, 2026 and a white paper within a year.

On February 12, 2026 the New York Public Service Commission ("PSC") issued an Order Instituting Proceeding and Soliciting Comments in Case 26-E-0045, Proceeding on Motion of the Commission to Address Interconnection Reforms for Large Loads. The order asks how large electric loads, including data centers, should be integrated into the grid. It is a policy proceeding, not a rule: no requirement on any project follows from it yet.

N.Y. PSC Case 26-E-0045, Order Instituting Proceeding and Soliciting Comments (Feb. 12, 2026)