NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…
MediumNew York

New York regulators decline to cap solar and storage interconnection costs, require utility cost reporting

At its August 13, 2026 session the Public Service Commission declined to cap developers' interconnection upgrade costs and instead required utility cost and study-timeline reporting, with tariff amendments effective October 1, 2026 and annual filings from March 31, 2027, according to the Department and a copy of the order.

On August 13, 2026, the New York Public Service Commission ("PSC") acted in Cases 24-E-0621 and 24-E-0415 on the cost and timing of interconnecting distributed energy resources, and the order copy read for this briefing is headed "Order on Interconnection Costs and Study Timelines" and "Issued and Effective August 17, 2026." The Commission declined to adopt a proposed 115 percent limit on developer payment obligations and declined to establish utility performance metrics, and instead required utilities to report cost and study-timeline data and to propose better cost estimates. The Department of Public Service's session summary states that the Commission directed utilities to file tariff amendments that will take effect by October 1, 2026, a date that has now passed.

N.Y. Pub. Serv. Comm'n, Cases 24-E-0621 and 24-E-0415 (Aug. 13, 2026 session; order dated Aug. 17, 2026 per copy)