LatestBriefings
NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
MediumNew York

New York regulators decline to cap solar and storage interconnection costs, require utility cost reporting

At its August 13, 2026 session the Public Service Commission declined to cap developers' interconnection upgrade costs and instead required utility cost and study-timeline reporting, with tariff amendments effective October 1, 2026 and annual filings from March 31, 2027, according to the Department and a copy of the order.

On August 13, 2026, the New York Public Service Commission ("PSC") acted in Cases 24-E-0621 and 24-E-0415 on the cost and timing of interconnecting distributed energy resources, and the order copy read for this briefing is headed "Order on Interconnection Costs and Study Timelines" and "Issued and Effective August 17, 2026." The Commission declined to adopt a proposed 115 percent limit on developer payment obligations and declined to establish utility performance metrics, and instead required utilities to report cost and study-timeline data and to propose better cost estimates. The Department of Public Service's session summary states that the Commission directed utilities to file tariff amendments that will take effect by October 1, 2026, a date that has now passed.

N.Y. Pub. Serv. Comm'n, Cases 24-E-0621 and 24-E-0415 (Aug. 13, 2026 session; order dated Aug. 17, 2026 per copy)

More on New York: rulebook · compliance calendar · funding and incentives · open comment periods

New York regulators decline to cap solar and storage interconnection costs, require utility cost reporting — EnvironmentalShortcut