NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…
MediumNew York

New York City begins fining owners whose sidewalk sheds stand without façade repair progress

A Buildings Department rule in force since August 13 sets $5,000 to $20,000 penalties for missed façade repair milestones and requires an engineer's or architect's progress report at each shed renewal.

Owners of New York City buildings wrapped in sidewalk sheds now pay for every month the shed stands without repair work, and face fixed penalties if façade repairs miss set deadlines. The New York City Department of Buildings (“DOB”) adopted N.Y.C. Rules, tit. 1, § 102-07, effective August 13, 2026, to carry out Local Law No. 48 (2025) and Local Law No. 51 (2025), and set the related filing fees in N.Y.C. Rules, tit. 1, § 101-03.

N.Y.C. Rules, tit. 1, § 102-07 (eff. Aug. 13, 2026); N.Y.C. Rules, tit. 1, § 101-03; N.Y.C. Admin. Code §§ 28-220.1, 28-220.2.1; N.Y.C. Local Law No. 48 (2025); N.Y.C. Local Law No. 51 (2025)