NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
MediumNew York

New York wind and solar projects face separate state siting and grid connection clocks

State siting permits for large wind and solar projects run on statutory deadlines, while grid connection runs on the grid operator's separate study cycle, which those deadlines do not govern.

The application window for the New York Independent System Operator's ("NYISO") next interconnection cluster study was scheduled to close on September 14, 2026, having opened on July 31, 2026, under the preliminary schedule NYISO noticed on December 11, 2025 pursuant to Section 40.5.1.3 of Attachment HH to its Open Access Transmission Tariff. The window is the point of entry to the grid for new generation and storage projects, and the study that follows sets the terms on which they can connect. The scheduled close came six months after the State's consolidated siting regulations, 16 NYCRR Parts 1100, 1101 and 1102, took effect on March 9, 2026.

Pub. Serv. Law Art. VIII, § 142; 16 NYCRR Parts 1100–1102; NYISO OATT Att. HH