New York wind and solar projects face separate state siting and grid connection clocks
State siting permits for large wind and solar projects run on statutory deadlines, while grid connection runs on the grid operator's separate study cycle, which those deadlines do not govern.
Under a preliminary schedule that the New York Independent System Operator ("NYISO") noticed on December 11, 2025 pursuant to Section 40.5.1.3 of Attachment HH to its Open Access Transmission Tariff, the application window for NYISO's next interconnection cluster study was to open on July 31, 2026 and close on September 14, 2026. Under the same tariff section, NYISO provides the actual start date later, 60 days before the scheduled presentation of the prior cluster study's report. The window is the point of entry to the grid for new generation and storage projects, and the study that follows sets the terms on which they can connect. The State's consolidated siting regulations, 16 NYCRR Parts 1100, 1101 and 1102, took effect on March 9, 2026.
Pub. Serv. Law Art. VIII, § 142; 16 NYCRR Parts 1100–1102; NYISO OATT Att. HH