NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
HighConnecticut

Connecticut bars state solar approvals in towns above set land-area shares until July 2027

A temporary bar on Siting Council solar approvals in certain towns runs to July 1, 2027, and new emergency-contact and incident-reporting duties for generating facilities start October 1, 2026.

Public Act 26-127 (House Bill 5340, "An Act Concerning Renewable Power Generation"), which the Act itself records as approved on June 4, 2026, contains two sets of provisions that bear directly on generating facilities in Connecticut: a temporary bar on approvals by the Connecticut Siting Council (the "Council") of solar photovoltaic facilities in municipalities that already host a defined share of Council-approved solar, and emergency-contact, training, reporting and jurisdictional provisions that take effect on October 1, 2026. Both will be read against schedules, lease terms and financing conditions written before the Act existed.

Pub. Act 26-127 (HB 5340) §§ 12, 13, 16, 17; Conn. Gen. Stat. §§ 16-50i, 16-50k, 16-50l