LatestBriefings
NJ · MediumNew Jersey holds October 15 hearings on a tighter power plant carbon cap from…PA · MediumPennsylvania requires proof of a water supplier before towns give final appro…PA · MediumPennsylvania board to consider stricter protection for 16 stream basins on Oc…NY · MediumNew York court blocks commercial tax class for vacant residential lots outsid…NJ · LowDelaware River basin proposal would make New Jersey water suppliers report th…NY · MediumNew York high court upholds SoHo and NoHo conversion fee; Supreme Court confe…NY · HighNew York City adopts fast-track land-use review and housing appeals board rul…PA · HighFederal: Philadelphia, Pittsburgh and central Pennsylvania counties may face…NY · MediumNew York appeals court holds brownfield cleanup kept Buffalo scrap yard's gra…NJ · LowNew Jersey Meadowlands authority sets October 20 hearing on changes to Kearny…
MediumConnecticut

Connecticut approves Ellington orchard solar as farm agency says it cannot review non-prime soils

The Siting Council approved a 4.99-megawatt array on an orchard with soils of statewide importance, which fall outside the agriculture department's review, and applied the 2026 emergency-contact rule.

Solar developers on Connecticut farmland that is productive but not mapped as prime face no state agriculture determination, and they now also face a standard emergency-contact condition. On September 17, 2026, the Connecticut Siting Council (the “Council”), the state body that approves power facilities in place of local zoning, ruled in Greenskies Clean Energy LLC, Petition No. 1711 (Conn. Siting Council Sept. 17, 2026), that a 4.99-megawatt (AC) solar facility on an orchard on Schoolhouse Road in Ellington “would not have a substantial adverse environmental effect,” approving it by declaratory ruling under Conn. Gen. Stat. § 16-50k with 22 conditions.

Greenskies Clean Energy LLC, Petition No. 1711 (Conn. Siting Council Sept. 17, 2026); Conn. Gen. Stat. § 16-50k(a); Conn. Pub. Act No. 26-127, §§ 11, 13 (2026)

More on Connecticut: rulebook · compliance calendar · funding and incentives · open comment periods

Connecticut approves Ellington orchard solar as farm agency says it cannot review non-prime soils — EnvironmentalShortcut