NJ · MediumNew Jersey weighs no base incentive for small farm solar projects that join c…NJ · LowNew Jersey Turnpike Authority picks five sites near its highways for possible…NJ · HighNew Jersey's top court says waterfront permits that change footprints must ad…NY · MediumNew York's top court rules objections to a missing summons are waived unless…CT · MediumConnecticut legislative panel approves tighter power plant carbon cap set for…MediumNew Jersey proposes sewer planning for 43.4 more acres of a Medford Township…NY · MediumNew York's top court rejects landlords' challenge to ban on refusing Section…NY · MediumNew York approves first construction plans for Propel NY power line on Long I…NJ · MediumNew Jersey lets community solar pilot projects sign up subscribers anywhere i…NJ · MediumFederal: Draft homeland security procedures would exempt grants under $5 mill…
LowConnecticut

Connecticut wetlands board members must finish state training by January 2027; denial standards unchanged

New training duties for local wetlands boards do not change the evidence a denial requires, so the record built at the hearing remains the basis of review on appeal.

Under Conn. Gen. Stat. § 22a-42(d), as amended by Public Act 25-73, each member of and staff person to a municipal inland wetlands agency must, on and after January 1, 2026, complete the comprehensive training program developed by the Commissioner of Energy and Environmental Protection, and those serving on January 1, 2026 must complete it by January 1, 2027. Public Act 26-61 (Substitute House Bill 5334), approved May 20, 2026 and effective July 1, 2026, directs the Commissioner of Energy and Environmental Protection to use any state funds made available to the Department of Energy and Environmental Protection ("DEEP") for the preservation of riparian areas in the fiscal year ending June 30, 2027 to hire an employee to conduct training for inland wetlands commissions. Neither act changes the standards for a denial, and § 22a-42(d) provides that failure to complete the training does not affect the validity of any agency action. For applicants, the grounds for a denial, and the record on which it is reviewed, remain those set by the Inland Wetlands and Watercourses Act (the "Act") and the decisions construing it.

Conn. Gen. Stat. §§ 22a-41, 22a-42(d), 22a-42a, 22a-43; P.A. 25-73; P.A. 26-61

More on Connecticut: rulebook · compliance calendar · funding and incentives · open comment periods